Energy · Remote camp
Al Ain to Liwa
01Midnight power run to Liwa
نقل الطاقة إلى ليوا عند منتصف الليل
A remote operations camp deep in the Liwa crescent lost its standby power days before a critical phase. Two 1250 kVA gensets had to be on site and synchronized before the morning shift. A midnight departure from Al Ain was the only window that cleared the daytime heat and traffic and still met the deadline on site.
How we ran it
- 1Loaded two 1250 kVA silent gensets onto lowbeds at the Al Ain yard and rolled out at 23:40 to cross the desert corridor in the cool of night.
- 2Ran a lead and chase escort across roughly 220 km of highway and graded track into the dune belt.
- 3Set both units on prepared bases, paralleled them for 2.5 MW of continuous capacity with one unit held as live standby, and handed over before the 06:00 shift.
- 4Stood up a fuel plan with a bowser and scheduled top ups so the camp never dropped below a safe reserve.
- 5Arranged accommodation and messing for the install and standby crew so the team stayed on site through commissioning.
- 6In the weeks after, arranged flatbeds and transport for follow on plant and consumables as the camp scaled.
Outcome
Power was live before sunrise and the camp lost no shifts. The follow on transport work turned a one off mobilization into a standing supply line.
By the numbers
2 × 1250
kVA gensets
2.5 MW
paralleled output
220 km
overnight corridor
0
shifts lost
Equipment and crew
